02/02/22 | 2:00 p.m.

UPDATE ON CITY WALK BHAM PROJECT MILESTONES
  • Block A –  playground equipment installed on western end of Block A near 15th St.
  • Block A – top soil and planting mix in; will begin to install synthetic turf week of 2/7
  • Block B – food truck aisle partially constructed off 16th St.
  • Block B – shotcrete being placed in the bottom of the skate park bowl
  • Block B – pump track 75% complete
  • Block B – 11,000 sq ft roller rink concrete complete; perimeter fence being installed around roller rink
  • Block B – irrigation being completed; plantings, including magnolias are going in
  • Block C – labyrinth pavers installed
  • Block D – concrete surface around water fountains complete; paver installation next
  • Block D – roof on visitors center and restroom adjacent to BJCC complete; decorative concrete around stations progressing
  • Block E – grading and prep work beginning
  • Block F – concrete flat work being installed
  • Block G – 23rd-24th St pickleball court installation underway (north of 9th Ave by Uptown parking lot)
  • Block G – perimeter curbs being completed
  • Block G – preparation for dog park ongoing; dog park fence installation and concrete flat work being completed
  • Block G – southern end small restroom station walls poured; structural steel being installed
  • Block H – concrete flat work and excavation for pond ongoing
  • Block H – large station walls are poured and structural steel installation ongoing
  • Block H – prep for underway for playground equipment
  • 9th Ave between 19th and RAJ remains closed for stamped concrete installation and trench drain installation
  • Lighting remains in test mode as troubleshooting is being conducted. Access is limited due to the presence of construction equipment.