City Walk BHAM Project Update 05/25/22
Jennifer Solt2022-05-26T13:29:49-05:0005/25/22 Block A – framework in place for wayfinding signage; panels in civil rights area pending installation...
05/25/22 Block A – framework in place for wayfinding signage; panels in civil rights area pending installation...
05/12/22 Block A – wayfinding signage installation has begun; pine straw complete on landscape; signature benches to be installed...
04/01/22 Block A – Turf has been rolled; pickle ball court painted and netted; landscape is 95% complete, only things remaining are site furnishings, park benches, trash cans, etc....
02/02/22 Block B – 11,000 sq ft roller rink concrete complete; perimeter fence being installed around roller rink; Block B – irrigation being completed; Block C – labyrinth pavers installed...
01/04/22 Block A – Pavers for civil rights plaza complete along 16th St.; Pickleball court asphalt done, painting and netting next; Playground equipment installation happening now...
Birmingham’s newest destination will transform the area within the I-59/20 corridor into an environment that connects the city like never before...
Alabama Department of Transportation
East Central Region
100 Corporate Parkway Suite 450
Hoover, Alabama 35242
General Information
info@citywalkbham.com
(205) 458-8200
© Copyright 2024 | All Rights Reserved | Website designed and developed by 24 Communications