05/25/22
UPDATE ON CITY WALK BHAM PROJECT MILESTONES
- Block A – framework in place for wayfinding signage; panels in civil rights area pending installation
- Block B – concrete work in skate park finishing next week; doors installed; hardware / fixtures needed in medium station
- Block C – installing handrails; wayfinding signage and rule signage being installed
- Block D – working on visitor center- installing doors, finishing HVAC for visitor’s center, structural glass being installed, touch up painting ongoing; 9th avenue concrete to be complete in next couple of weeks
- Block E – wayfinding signage installation ongoing; landscaping 90% complete- adding mulch and pine straw
- Block F – wayfinding signage installation ongoing; handrails being installed around stage area; decomposed aggregate being installed; mulch and pine straw needed in landscape areas
- Block G – small station door installations and fixtures, toilet paper holders, hand dryers, etc.; landscaping on south side of parking lot ongoing
- Block H – playground equipment installed- pending swings; landscaping going in around pond; fountain installed in pond- pending power; concrete work-filling in previous access points; landscape underway- laying sod