03/01/22 | 2:00 p.m.

UPDATE ON CITY WALK BHAM PROJECT MILESTONES
  • Block A – landscaping and plantings have been installed
  • Block B – skate park bowls and pump track completed
  • Block B – concrete flat work in roller rink progressing
  • Block C – concrete flat work and sidewalks being installed, aggregate surfacing underway
  • Block D – tile surfaces being installed on fountain, continuing concrete flat work and sidewalk installation
  • Block D – fountain construction underway, to be followed by turf and landscaping
  • Block D – 9th Ave. decorative concrete paving underway
  • Block E – concrete flat work and sidewalks being installed
  • Block F – concrete flat work and sidewalks being installed
  • Block G – perimeter curbs being completed, asphalt to follow
  • Block G – dog park fence installation, concrete flat work and sidewalks being completed
  • Block G – Southern end small restroom station nearing completion
  • Block H – concrete flat work and excavation for pond ongoing
  • 9th Ave. between 19th and RAJ remains closed for stamped concrete installation and trench drain installation
  • 22nd St. between 9th Ave. and the alleyway closed for water line access and pressure testing
  • Lighting remains in test mode as troubleshooting is being conducted. Access is limited due to the presence of construction equipment.