03/01/22 | 2:00 p.m.
UPDATE ON CITY WALK BHAM PROJECT MILESTONES
- Block A – landscaping and plantings have been installed
- Block B – skate park bowls and pump track completed
- Block B – concrete flat work in roller rink progressing
- Block C – concrete flat work and sidewalks being installed, aggregate surfacing underway
- Block D – tile surfaces being installed on fountain, continuing concrete flat work and sidewalk installation
- Block D – fountain construction underway, to be followed by turf and landscaping
- Block D – 9th Ave. decorative concrete paving underway
- Block E – concrete flat work and sidewalks being installed
- Block F – concrete flat work and sidewalks being installed
- Block G – perimeter curbs being completed, asphalt to follow
- Block G – dog park fence installation, concrete flat work and sidewalks being completed
- Block G – Southern end small restroom station nearing completion
- Block H – concrete flat work and excavation for pond ongoing
- 9th Ave. between 19th and RAJ remains closed for stamped concrete installation and trench drain installation
- 22nd St. between 9th Ave. and the alleyway closed for water line access and pressure testing
- Lighting remains in test mode as troubleshooting is being conducted. Access is limited due to the presence of construction equipment.