01/04/22 | 2:00 p.m.

UPDATE ON CITY WALK BHAM PROJECT MILESTONES
  • Block A – Pavers for civil rights plaza complete along 16th St
  • Block A – Pickleball court asphalt done, painting and netting next
  • Block A – Playground equip install happening now
  • Block B – Skate park construction underway, pool shotcrete being placed 1/5/22, roller rink concrete poured 1/8/22
  • Block C – Hardscape completed, turf to install
  • Block D – Work continues on amphitheater and elevated area, visitors center and restroom under construction
  • Block G – 23rd-24th St Pickleball court installation underway north of 9th Ave by Uptown parking lot
  • Block G – Southern end small station walls being poured 1/5/22
  • Block H – Excavation for pond ongoing, site grading, large station footings being poured
  • 9th Ave between 19th and RAJ closed for stamped concrete installation.
  • Lighting remains in test mode. Access is limited due to the presence of construction equipment.